Cut bottom chord of roof truss for pulldown stairs

Cut bottom chord of roof truss for pulldown stairs

New postby pbennett1 on Tue Jun 23, 2009 7:56 pm

Jerry,
The 9 year old townhouse inspection today has new stairs installed in the field and not during the original construction. The installer cut/modified the bottom chord, and boxed out the framing. Joist hangers are missing and the connections consist of deck screws.

What is the proper procedure for the repair sequence?
Get an engineer for evaluation and repair recommendations
Get a qualified contractor to implement the engineer's repairs
Have the engineer return and sign off on the contractor's repairs.

I would like clarification on the proper field procedure for the above.
You do not have the required permissions to view the files attached to this post.
pbennett1
 
Posts: 12
Joined: Tue May 12, 2009 7:30 pm

Re: Cut bottom chord of roof truss for pulldown stairs

New postby Jerry Peck - Codeman on Tue Jun 23, 2009 8:32 pm

pbennett1 wrote:What is the proper procedure for the repair sequence?
Get an engineer for evaluation and repair recommendations
Get a qualified contractor to implement the engineer's repairs
Have the engineer return and sign off on the contractor's repairs.


This is the best was to call it out as it avoids giving someone else control over your evaluation and simply states what someone needs to do: "Have truss engineer design appropriate repairs, and, after repairs have been completed, provide an engineering letter stating that the repairs have been completed in accordance with the engineering design. The engineer needs to have signed and sealed the engineering design and the follow-up letter."

That way the truss engineer designs the repairs, someone - supposedly a licensed contractor - makes the repairs, then the engineer inspects the repairs and issues an engineer's letter stating that all is now okay.

Many years ago I would recommend a structural engineer design appropriate repairs ... and that was it. That was also when I did re-inspections - once while doing a re-inspection I stated that the trusses had not been repaired, the owner pulled out an engineer's letter and said "Here, this is the engineering letter and design you told me to get.", as though that would take care of the broken truss. That did bring it to my attention that the only thing I had said to do was to get an engineer's letter for the repair - and to *me* - implied in that was *and have it repaired*, but I had not said that and they did not do that.

Then sometime later someone wanted me to inspect the repairs to see if the repairs were in accordance with the engineering. That is when I added the part about getting the engineer's letter stating that the repairs were completed in accordance with the engineering and all is okay.

To us, some things are common sense and are "implied", to others, those same things need to be stated to eliminate any misunderstanding.
Jerry Peck - CodeMan
AskCodeMan.com
Construction Litigation Consultant - Retired
Construction and Code Consultant - Semi Retired
User avatar
Jerry Peck - Codeman
Site Admin
 
Posts: 1199
Joined: Fri Dec 12, 2008 12:06 pm


Return to Structure: Footings, foundation walls, floor framing, wall framing, ceiling framing, roof framing (rafters & engineered trusses)



Who is online

Users browsing this forum: No registered users and 3 guests